Installing an energy pack option for HPE Smart Storage

Prerequisites

Before you perform this procedure, make sure that you have the following items available:

  • T-10 Torx screwdriver

  • The components included with the hardware option kit

Procedure
  1. Power down the server.
  2. Remove all power:
    1. Disconnect each power cord from the power source.
    2. Disconnect each power cord from the server.
  3. Do one of the following:
    • Extend the server from the rack.
    • Remove the server from the rack.
  4. Remove the access panel.
  5. Remove the air baffle.
  6. Remove the fan cage.
  7. Install the energy pack option.
  8. Route and connect the cable.
    CAUTION:

    Do not connect the energy pack while the server is operating. Verify that all power to the server has been removed.

  9. Install the fan cage.
  10. Install the access panel.
  11. Install the server into the rack.
  12. Connect each power cord to the server.
  13. Connect each power cord to the power source.
  14. Power up the server.