Prerequisites
Before you perform this procedure, make sure that you have the following items available:
Procedure
-
Power down the server.
-
Remove all power:
- Disconnect each power cord from the power source.
- Disconnect each power cord from the server.
-
Disconnect all peripheral cables from the server.
-
Do one of the following:
-
Remove the access panel.
-
Remove the PCI air baffle.
-
Remove the system air baffle.
-
Disconnect all the power supply cables connected to the system board.
-
Remove the existing power supply.
-
Install the ATX 550W non-hot-plug power supply.
-
Connect the power supply cables.
-
Install the system air baffle.
-
Install the PCI air baffle.
-
Install the access panel.
-
Do one of the following:
-
Connect all peripheral cables to the server.
-
Connect each power cord to the server.
-
Connect each power cord to the power source.
-
Power up the server.
The installation is complete.