Prepare the server for rack installation

Prerequisites
Before you perform this procedure:
Procedure
  1. Power down the server.

    If you are physically powering down the server, open the front bezel to access the power button. Close the bezel after the server is powered down.

  2. Remove all power:
    1. Disconnect each power cord from the power source.
    2. Disconnect each power cord from the server.
  3. Disconnect all peripheral cables from the server.
  4. If installed, unlock and remove the security padlock and/or the Kensington security lock.

    For more information, see the lock documentation.

  5. Position the tower server for hardware configuration.
  6. Remove the chassis feet.
    1. Loosen the screws on the chassis.
    2. Detach the chassis feet.

    Removing the chassis feet