Prerequisites
Before installing this option, be sure that you have the following:
Procedure
-
Power down the
server (Power down the server).
-
Remove all power:
- Disconnect each power cord from the power source.
- Disconnect each power cord from the
server.
-
Do one of the following:
- Extend the
server from the rack (Extend the server from the rack).
- Remove the
server from the rack (Remove the server from the rack).
-
Remove the access panel (Remove the access panel).
-
Remove the primary PCI riser cage (Remove the primary PCI riser cage).
-
If needed, remove any expansion boards installed in the riser cage.
-
Remove the existing riser board from the riser cage.
-
Install the M.2 riser board.
-
Remove the screw securing the standoff on the riser.
-
Install the M.2 drives.
-
Install the following, as needed:
-
Install the primary PCI riser cage (Install the primary PCI riser cage).
-
Install the access panel (Install the access panel).
-
Install the
server in the rack.