Installing the 4 LFF display port/USB module

Prerequisites

Before installing this option, be sure you have the following:

  • The components included with the hardware option kit

  • T-10 Torx screwdriver

Procedure
  1. Power down the server (Power down the server).
  2. Remove all power:
    1. Disconnect each power cord from the power source.
    2. Disconnect each power cord from the server.
  3. Do one of the following:
    1. Extend the server from the rack (Extend the server from the rack).
    2. Remove the server from the rack (Remove the server from the rack).
  4. Remove the access panel (Remove the access panel).
  5. Using a Torx T-10 screwdriver, remove the 4 LFF display port/USB blank.

    Removing the 4 LFF display port/USB blank

  6. Install the 4 LFF display port/USB module.

    Installing the 4 LFF display port/USB module

  7. Route and connect the cable.

    4 LFF display port/USB cable routing

  8. Install the access panel (Install the access panel).
  9. Install the server in the rack.
  10. Connect each power cord to the server.
  11. Connect each power cord to the power source.
  12. Power up the server (Power up the server).