Prerequisites
Install the processor mezzanine tray to support four processors in the server.
Before you perform this procedure, make sure that you have the following items available:
Procedure
-
Power down the server.
-
Remove all power:
- Disconnect each power cord from the power source.
- Disconnect each power cord from the
server.
-
Do one of the following:
-
Remove the access panel (Removing the access panel).
CAUTION: Do not operate the
server for long periods with the access panel open or removed. Operating the
server in this manner results in improper airflow and improper cooling that can lead to thermal damage.
-
Remove the air baffle (Removing the air baffle).
-
Install the processors onto the processor mezzanine tray sockets (Installing a processor).
-
Install the DIMMs onto the processor mezzanine tray DIMM slots (Installing a DIMM).
-
Install the processor mezzanine tray.
-
Install the air baffle (Installing the air baffle).
-
Install the access panel (Installing the access panel).
-
Install the server into the rack (Installing the server into the rack).
-
Connect each power cord to the
server.
-
Connect each power cord to the power source.
-
Power up the server.