Prerequisites
Before you perform this procedure, make sure that you have the following items available:
T-15 Torx screwdriver
T-10 Torx screwdriver
FlexibleLOM riser cage
Procedure
-
If installed,
remove the front bezel.
-
Power down the server.
-
Remove all power:
- Disconnect each power cord from the power source.
- Disconnect each power cord from the server.
-
Disconnect all peripheral cables from the server.
-
Do one of the following:
-
Remove the access panel.
-
Remove the primary riser cage.
-
Remove the FlexibleLOM blank.
-
Install the FlexibleLOM adapter.
-
Install the FlexibleLOM riser cage.
-
Install the access panel.
-
Install the server into the rack.
-
Connect the LAN segment cables.
-
Connect all peripheral cables to the server.
-
Connect each power cord to the server.
-
Connect each power cord to the power source.
-
Power up the server.
-
If removed,
install the front bezel.
The installation is complete.