Prerequisites
Before you perform this procedure:
Procedure
-
Remove the front bezel.
-
Power down the server.
-
Remove all power:
- Disconnect each power cord from the power source.
- Disconnect each power cord from the
server.
-
Disconnect all peripheral cables from the server.
-
Do one of the following:
-
Remove the access panel.
-
Remove the air baffle.
-
If installed,
remove the fan cage.
-
Remove the drive cage blank from box 2.
Retain the blank for future use.
-
Install the drive cage in box 2.
-
Remove the PCI blank retainer.
-
Remove the PCI slot blanks opposite slots 1 and 3.
-
Remove the PCI board screws opposite slots 1 and 3.
-
Observe the guidelines for managing cables.
-
Connect the NMVe SSD data cables to the riser boards, and then secure the cables in the cable clip.
-
Install the NVMe riser boards in slots 1 and 3.
-
Make sure that the boards are firmly seated in the slots.
-
Install the PCI blank retainer.
-
Connect the drive cables:
-
If the fan cage was removed, do the following:
- Make sure that all the system cables that are routed through the front cable channel are properly secured in the metal cable tabs. This is done to prevent system damage due to cables being inadvertently caught under the fan cage.
- Install the fan cage.
-
Install the air baffle.
-
Install the access panel.
-
Do one of the following:
-
Connect all peripheral cables to the server.
-
Connect each power cord to the server.
-
Connect each power cord to the power source.
-
Power up the server.
-
Install the NVMe SSDs.
-
Install the front bezel.
The installation is complete.